Project Updates
Construction Schedule Update (July 19, 2010):
** Work on the Columbia Heights construction project in Final Phase. **
Update
- Final phase of construction on 14th Street at north of Park Rd and continues to the Project limits at Newton St.
- Work in progress on concrete Island on 14th St. between Park Rd and Monroe St.
- All base asphalt paving completed on project.
- Final surface asphalt paving completed on 14th St. from Columbia Rd. to Park Rd.
- Final Streetlight and Traffic Light Installation underway
- Side walk reconstruction and paver installation on west side of 14th St from Park rd to Newton Street in progress.
- Landscaping.
Changes in Traffic Pattern on 14th Street and Park Road:
- EB Park Rd is now open to traffic from 14th St. Right turn from NB 14th St is now open.
- WB Park Rd traffic from Holmead Pl can only turn right onto NB 14th St. at the 14th St. intersection.
- No thru traffic for WB Park Rd. across 14th St. to Park Rd (west).
- Motorist from the east of 14th St. wishing to go west on Park Rd may now use Kenyon St.
| On-going Construction Week of July 19 thru July 24: | |
| Location (1): | 14th Street- from Park Rd to Newton (West side) |
| Work Items: | Sidewalk Paver installation |
| Location (2) | 14th St- from Park Rd to Monroe St. |
| Work Items: | Median installation and final surface asphalt paving (to Newton St.) |
| Location (3): | 14th St- from Monroe St. to Newton (West side) |
| Work Items: | Excavation of existing sidewalk and place PCC base for Sidewalk Paver Installation. |
| Location (4): | 14th St- from Park Rd to Monroe St. |
| Work Items: | Granite/concrete/planter median installation and final surface asphalt paving (to Newton St.) |
| Location (5): | 14th St- from Columbia Rd to Newton |
| Work Items: | Pavement marking and general site cleanup. |
| Location (6): | 14th St- from Park Rd to Newton (west side) |
| Work Items: | Signal lights and Streetlights |
| Location (7): | 14th St- from Columbia Rd to Newton |
| Work Items: | Signs. |
| Location (8): | 14th St- from Columbia Rd to Newton |
| Work Items: | Punch list work. |
Upcoming Work
- Punchlist work, general clean up and Project close
Construction Schedule & Timeline:
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | complete | complete | complete | N/A | In progress | 06/2010 |
| Park Rd to Monroe St. | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 07/2010 | 07/2010 |
| Monroe St to Newton St. | 06/2010 | 07/2010 | 07/2010 | 07/2010 | 05/2010 | 07/2010 |
| Columbia Rd to Newton St. | Punchlist | Punchlist | Punchlist | Punchlist | Punchlist | Punchlist |
Maintenance of Traffic (MOT) & Impact:
- West curb lane SB 14th Street will be closed for the road reconstruction and Paving work.
- One lane of traffic in each direction on the east half of 14th street will be maintained at all times during construction.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restritcted.
- Pedestrian Access to businesses along the side walks will continue to be maintained.
- Most crosswalks are now open, however, Traffic Safety Officers at Intersections during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular traffic where needed.
Construction Schedule Update (June 28, 2010):
** Work on the Columbia Heights construction project in Final Phase. **
Update
- Pepco crew completes utility work.
- Concrete intersection work at east half of Kenyon and 14th St. completed.
- Final grading work and paving on NB 14th St just south of Kenyon St.; Traffic switched to curb lanes between Irving St and Kenyon St. when completed
- Median strip work on 14th St. between mid block DCUSA to Kenyon Street to follow.
- Road Reconstruction work completed in the median lane of 14th St. from Park Rd to Monroe St.
- Traffic switched to east side from Park Rd to Newton St.
- Excavation, curb installation, storm inlet installation on west half of 14th St form Park Rd to Monroe St in progress.
- Concrete Traffic Barriers remain in place from Irving St. to Newton St. to protect the excavation; and will be removed by Friday July 02, 2010 for the July 4 weekend.
- Concrete intersection work at NW corner of Park Rd and 14th St begins; concrete to be placed on Wednesday June 30, 2010.
Changes in Traffic Pattern on 14th Street and Park Road:
- With the Concrete work at the NW corner of the 14th St. & Park Rd. intersection traffic on Park Rd (west of 14th St) will be restricted to one lane only from Monday June 28 thru Friday July 02; Intermittent stoppages to facilitate egress and ingress of trucks will be permitted but will stoppages will last no more than 5 minutes at a time when that occurs.
- EB Park Rd is now open to traffic from 14th St. Right turn from NB 14th St is now open.
- WB Park Rd traffic from Holmead can only turn right onto NB 14th St. at the 14th St. intersection.
- No thru traffic on Park Rd. (east) across 14th St. to Park Rd (west).
- Motorist from the east of 14th St. may use Monroe St and Kenyon St for access to SB 14th St & Park Rd (west of 14th St.)
| On-going Construction Week of June 07 thru June 19: | |
| Location (1): | 14th Street- from Park Rd to Newton (West side) |
| Work Items: | Storm inlets, granite curb, Roadway excavation, aggregate base & base asphalt paving work. |
| Location (2): | Metro Plaza. |
| Work Items: | Mosaic art Medallion frames installation. |
| Location (3) | 14th St- DCUSA to Kenyon St |
| Work Items: | Mid strip paving; switch traffic to east side when completed. |
| Location (4): | NW corner of Park Rd and 14th St intersection |
| Work Items: | Colored Concrete & band |
| Location (5): | Median Strip - 14th St mid block DCUSA to Kenyon St |
| Work Items: | Paving and Colored Concrete & band; Switch traffic to the east when competed. |
| Location (6): | NW corner of Park Rd and 14th St intersection |
| Work Items: | Roadway reconstruction – base asphalt paving. |
Upcoming Work
- Colored Concrete - 14th Street intersections Kenyon St. and Park Rd.
- Traffic switch on 14th Street.
Construction Schedule & Timeline:
14th Street, NW, East Side (North Bound):
| Activity | Location | Estimated Start Date | Estimated End Date (revised) |
| Full Depth Roadway Reconstruction | 14th Street (from Irving St. to Kenyon St.) | In progress | completed |
| Full Depth Roadway Reconstruction | 14th Street (from Monroe St. to Newton St.) | In progress | completed |
| Full Depth Roadway Reconstruction | Monroe Street (East) south half & intersection | In progress | completed |
| Full Depth Roadway Reconstruction | Park Rd. to Monroe St. (East) north half | 06/09/10 | completed |
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | complete | complete | complete | N/A | In progress | 06/2010 |
| Park Rd to Monroe St. | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 07/2010 | 07/2010 |
| Monroe St to Newton St. | 06/2010 | 07/2010 | 07/2010 | 07/2010 | 05/2010 | 07/2010 |
Maintenance of Traffic (MOT) & Impact:
- West curb lane SB 14th Street will be closed for the road reconstruction and Paving work.
- One lane of traffic in each direction on the east half of 14th street will be maintained at all times during construction.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restritcted.
- Pedestrian Access to businesses along the side walks will continue to be maintained.
- Most crosswalks are now open, however, Traffic Safety Officers at Intersections during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular traffic where needed.
Construction Schedule Update (June 21, 2010):
** Work on the Columbia Heights construction project in Final Phase. **
Update
- Construction of Colored Concrete intersection at the 14th St & Irving St completed.
- Except for final surface, Road Reconstruction work is completed on 14th St. from Columbia Road to Irving St.
- Pavement Excavation and Road Reconstruction work continues at south side Monroe St (east) and NB 14th St.
- Traffic switch to curbs lanes to begin.
- Road Reconstruction work begins in the median lane of 14th St. from Park Rd to Monroe St.
- Solar panel installation at Metro Plaza in progress.
- Concrete Traffic Barriers remain in place from Irving St. to Newton St. to protect the excavation; and will be removed/relocated as needed.
- Paver band installation work continues at the Metro Plaza; public art medallion frames installation begins.
Changes in Traffic Pattern on 14th Street and Park Road (east side):
- With the Pepco Utility work at the intersection of 14th St & Park Rd effective from Friday, May 28, until further notice,
the following traffic restrictions at 14th St. & Park Rd. intersection are in place:- EB Park Rd continues to be closed to thru traffic going east from NB 14th St; No right turn onto Park Rd from NB 14th St.
- WB Park Rd traffic from Holmead can only turn right onto NB 14th St at the 14th St intersection.
- No thru traffic on Park Rd (east) across 14th St to Park Rd (west).
- Motorist from the east of 14th St may use Monroe St and Kenyon St for access to SB 14th St & Park Rd (west of 14th St.)
| On-going Construction Week of June 21 thru June 26: | |
| Location (1): | Monroe St. (east of 14th St) - south half & 14th St just south of Monroe St. |
| Work Items: | Roadway reconstruction- aggregate base & base asphalt paving work. |
| Location (2): | Metro Plaza. |
| Work Items: | Mosaic art Medallion frames installation |
| Location (3) | DCUSA |
| Work Items: | Sidewalk paver repair and paver band installation. |
| Location (4): | SB 14th St (Irving St to Park Rd) |
| Work Items: | Roadway excavation and reconstruction; concrete intersection. |
Upcoming Work
- Colored Concrete - 14th Street intersections at Kenyon St. and Park Rd.
- Traffic switch on 14th Street.
Construction Schedule & Timeline:
14th Street, NW, East Side (North Bound):
| Activity | Location | Estimated Start Date | Estimated End Date (revised) |
| Sidewalk Pavers Installation | Monroe St. to Newton St. | 05/01/10 | Completed* |
| Full Depth Roadway Reconstruction | 14th Street (from Irving St. to Kenyon St.) | In progress | June, 2010 |
| Full Depth Roadway Reconstruction | 14th Street (from Monroe St. to Newton St.) | In progress | completed |
| Full Depth Roadway Reconstruction | Monroe Street (East) south half & intersection | In progress | 06/12/10 |
| Full Depth Roadway Reconstruction | Park Rd. to Monroe St. (East) north half | 06/09/10 | 06/15/10 |
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | complete | complete | complete | N/A | In progress | 06/2010 |
| Park Rd to Monroe St. | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 06/2010 |
| Monroe St to Newton St. | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 to 06/2010 |
Maintenance of Traffic (MOT) & Impact:
- East curb lane and inside right lane NB 14th Street will be closed for the road reconstruction and Paving work.
- One lane of traffic in each direction on the west half of 14th street will be maintained at all times during construction.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restritcted.
- Pedestrian Access to businesses along the side walks will continue to be maintained.
- Pickup & Drop off of riders to the bus stops on 14th Street at Park Rd will temporarily returned to its original location near the Tivoli Theatre.
- Traffic Safety Officers at Intersections during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular traffic.
Construction Schedule Update (June 7, 2010):
** Work on the Columbia Heights construction project in Final Phase. **
Update
- Construction of Colored Concrete intersection continues at 14th St & Irving St continues; construction on west side in progress.
- Pavement Excavation and Road Reconstruction work begins on SB 14th St. (i.e. east side) from Columbia Road to Park Road.
- Concrete Traffic Barriers remain in place from Irving street to Newton to protect the excavation; and will be removed/relocated as needed.
- Paver installation work is completed at the Metro Plaza at 3030 14th Street except for areas marked for decorative banding and public art medallion frames.
- Specialty Lighting installation at Metro Plaza and in project area (Irving St, Park Rd and Kenyon St.)
- Solar panel installation at Metro Plaza in progress.
- Repair of existing pavers, trees and paver band installation around DCUSA.
Changes in Traffic Pattern on 14th Street and Park Road (east side):
- With the Pepco Utility work at the intersection of 14th St & Park Rd effective from Friday, May 28 thru on or about Saturday June 19, 2010,
the following traffic restrictions at 14th St. & Park Rd. intersection are in place:- EB Park Rd continues to be closed to thru traffic going east from NB 14th St; No right turn onto Park Rd from NB 14th St.
- WB Park Rd traffic from Holmead can only turn right onto NB 14th St at the 14th St intersection.
- No thru traffic on Park Rd (east) across 14th St to Park Rd (west).
- Motorist from the east of 14th St may use Monroe St and Kenyon St for access to SB 14th St & Park Rd (west of 14th St.)
| On-going Construction Week of June 07 thru June 19: | |
| Location (1): | NB 14th St. from Park Rd to Monroe St. |
| Work Items: | Pepco Utility work continues. |
| Location (2): | SB 14th St just south of Irving St & Irving St SW corner. |
| Work Items: | Roadway excavation and reconstruction; concrete intersection. |
| Location (3): | Monroe St. (east of 14th St) - south half & 14th St just south of Monroe St. |
| Work Items: | Roadway reconstruction- aggregate base & base asphalt paving work. |
| Location (4): | Metro Plaza. |
| Work Items: | Specialty Lighting & Solar Panel installation. |
| Location (5) | DCUSA |
| Work Items: | Sidewalk paver repair and paver band installation. |
| Location (6): | NB 14th St. (i.e. east side) from Kenyon St. to Monroe St. |
| Work Items: | Pepco & Verizon utility work. |
| Location (7): | SB 14th St (Irving St to Park Rd) |
| Work Items: | Roadway excavation and reconstruction; concrete intersection. |
Upcoming Work
- Colored Concrete - 14th Street intersections at (1) Irving St. & (2) Kenyon St. and Park Rd.
- Traffic switch on 14th Street.
Construction Schedule & Timeline:
14th Street, NW, East Side (North Bound):
| Activity | Location | Estimated Start Date | Estimated End Date (revised) |
| Sidewalk Pavers Installation | Monroe St. to Newton St. | 05/01/10 | Completed* |
| Full Depth Roadway Reconstruction | 14th Street (from Irving St. to Kenyon St.) | In progress | June, 2010 |
| Full Depth Roadway Reconstruction | 14th Street (from Monroe St. to Newton St.) | In progress | completed |
| Full Depth Roadway Reconstruction | Monroe Street (East) south half & intersection | In progress | 06/12/10 |
| Full Depth Roadway Reconstruction | Park Rd. to Monroe St. (East) north half | 06/09/10 | 06/15/10 |
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | complete | complete | complete | N/A | In progress | 06/2010 |
| Park Rd to Monroe St. | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 06/2010 |
| Monroe St to Newton St. | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 to 06/2010 |
Maintenance of Traffic (MOT) & Impact:
- East curb lane and inside right lane NB 14th Street will be closed for the road reconstruction and Paving work.
- One lane of traffic in each direction on the west half of 14th street will be maintained at all times during construction.
- One traffic lane on Irving Street will remain open at all times during construction.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restritcted.
- Pedestrian Access to businesses along the side walks will continue to be maintained.
- Pickup & Drop off of riders to the bus stops on 14th Street at Park Rd will temporarily returned to its original location near the Tivoli Theatre.
- Traffic Safety Officers at Intersections during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular traffic.
Construction Schedule Update (May 31, 2010):
** Work on the Columbia Heights construction project in Final Phase. **
Update
- Construction of Colored Concrete intersection continues at 14th St & Irving St continues; construction on east side completed, west side to begin.
- Construction of Colored Concrete intersection at Park Rd has begun.
- Pavement Excavation and Road Reconstruction work continues on NB 14th St. (i.e. east side) from Irving Street to Monroe Street.
- Concrete Traffic Barriers remain in place from Irving street to Newton to protect the excavation.
- Paver installation work is completed at the Metro Plaza at 3030 14th Street except for areas marked for decorative banding and public art medallion frames.
- Specialty Lighting installation at Metro Plaza and in project area (Irving St, Park Rd and Kenyon St.)
- Solar panel installation at Metro Plaza in progress.
Changes in Traffic Pattern on 14th Street and Park Road (east side):
- With the Pepco Utility work at the intersection of 14th St & Park Rd effective from Friday, May 28 thru on or about Saturday June 5, 2010,
the following traffic restrictions at 14th St. & Park Rd. intersection are in place:- EB Park Rd continues to be closed to thru traffic going east from NB 14th St; No right turn onto Park Rd from NB 14th St.
- WB Park Rd traffic from Holmead can only turn right onto NB 14th St at the 14th St intersection.
- No thru traffic on Park Rd (east) across 14th St to Park Rd (west).
- Motorist from the east of 14th St may use Monroe St and Kenyon St for access to SB 14th St & Park Rd (west of 14th St.)
| On-going Construction Week of May 31 thru June 5: | |
| Location (1): | NB 14th St. from Park Rd to Monroe St. |
| Work Items: | Pepco Utility work continues. |
| Location (2): | SB 14th St just south of Irving St & Irving St SW corner. |
| Work Items: | Roadway excavation and reconstruction; concrete intersection. |
| Location (3): | Monroe St. (east of 14th St) - south half & 14th St just south of Monroe St. |
| Work Items: | Roadway reconstruction- aggregate base & base asphalt paving work. |
| Location (4): | Metro Plaza. |
| Work Items: | Specialty Lighting & Solar Panel installation. |
| Location (5) | DCUSA |
| Work Items: | Sidewalk paver repair and paver band installation. |
| Location (6): | NB 14th St. (i.e. east side) from Kenyon St. to Monroe St. |
| Work Items: | Pepco & Verizon utility work. |
Upcoming Work
- Colored Concrete - 14th Street intersections at (1) Irving St. & (2) Kenyon St. and Park Rd.
- Traffic switch on 14th Street.
Construction Schedule & Timeline:
14th Street, NW, East Side (North Bound):
| Activity | Location | Estimated Start Date | Estimated End Date (revised) |
| Sidewalk Pavers Installation | Monroe St. to Newton St. | 05/01/10 | Completed* |
| Full Depth Roadway Reconstruction | 14th Street (from Irving St. to Kenyon St.) | In progress | June, 2010 |
| Full Depth Roadway Reconstruction | 14th Street (from Monroe St. to Newton St.) | In progress | completed |
| Full Depth Roadway Reconstruction | Monroe Street (East) south half & intersection | In progress | 06/12/10 |
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | complete | complete | complete | N/A | In progress | 06/2010 |
| Park Rd to Monroe St. | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 06/2010 |
| Monroe St to Newton St. | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 to 06/2010 |
Maintenance of Traffic (MOT) & Impact:
- East curb lane and inside right lane NB 14th Street will be closed for the road reconstruction and Paving work.
- One lane of traffic in each direction on the west half of 14th street will be maintained at all times during construction.
- One traffic lane on Irving Street will remain open at all times during construction.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restritcted.
- Pedestrian Access to businesses along the side walks will continue to be maintained.
- Pickup & Drop off of riders to the bus stops on 14th Street at Park Rd will temporarily returned to its original location near the Tivoli Theatre.
- Traffic Safety Officers at Intersections during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular traffic.
Construction Schedule Update (May 24, 2010):
** Work on the Columbia Heights construction project in Final Phase. **
Update
- Construction of Colored Concrete intersection continues at Irving St. & 14th St.
- Existing Pavement Excavation and Road Reconstruction work continues on NB 14th St. (i.e. east side) from Irving Street to Monroe Street.
- Concrete Traffic Barriers remain in place from Irving street to Newton to protect the excavation.
- Concrete Pavement Restoration work on Irving Street is completed.
- Paver installation work is completed at the Metro Plaza at 3030 14th Street except for areas marked for decorative banding and public art medallion frames.
- Specialty Lighting installation at Metro Plaza and in project area (Irving St, Park Rd and Kenyon St.)
- Solar panel installation at Metro Plaza in progress.
Changes in Traffic Pattern on 14th Street and Park Road (east side):
- With the Full depth asphalt paving construction on Park Rd starting from Monday, May 24 thru Saturday May 29, 2010,
the following traffic restrictions at 14th St. & Park Rd. intersection are in place:- Park Rd will be closed between 14th St and Holmead to through traffic;
Access to local traffic only will be allowed. - Monroe St (east of 14th St.) will be open and to be detour route for traffic to and from 14th Street.
- Park Rd will be closed between 14th St and Holmead to through traffic;
| On-going Construction Week of May 24 thru May 29: | |
| Location (1): | NB 14th St. from Park Rd to Monroe St. |
| Work Items: | Roadway reconstruction- aggregate base & base asphalt paving work. |
| Location (2): | Monroe St. (east of 14th St) - south half |
| Work Items: | Roadway reconstruction- aggregate base & base asphalt paving work. |
| Location (3) | Park Rd (east of 14th St.) |
| Work Items: | Pavement Excavation and reconstruction. |
| Location (4): | NB 14th St south of Irving St. |
| Work Items: | Pavement Excavation and reconstruction. |
| Location (5): | Irving St. (east of 14th St) - south half |
| Work Items: | Roadway reconstruction- aggregate base & base asphalt paving work. |
| Location (6): | Irving Street & Metro Plaza |
| Work Items: | Specialty Lighting & Solar Panel installation. |
| Location (7): | NB 14th St. (i.e. east side) from Kenyon St. to Monroe St. |
| Work Items: | Pepco & Verizon utility work. |
Upcoming Work
- Colored Concrete - 14th Street intersections at (1) Irving St. & (2) Kenyon St. and Park Rd.
Construction Schedule & Timeline:
14th Street, NW, East Side (North Bound):
| Activity | Location | Estimated Start Date | Estimated End Date (revised) |
| Sidewalk Pavers Installation | Monroe St. to Newton St. | 05/01/10 | Completed* |
| Full Depth Roadway Reconstruction | 14th Street (from Irving St. to Kenyon St.) | In progress | June, 2010 |
| Full Depth Roadway Reconstruction | 14th Street (from Monroe St. to Newton St.) | In progress | 05/22/10 |
| Full Depth Roadway Reconstruction | Monroe Street (East) | In progress | 05/29/10 |
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | complete | complete | complete | N/A | In progress | 06/2010 |
| Park Rd to Monroe St. | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 06/2010 |
| Monroe St to Newton St. | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 to 06/2010 |
Maintenance of Traffic (MOT) & Impact:
- East curb lane and inside right lane NB 14th Street will be closed for the road reconstruction and Paving work.
- One lane of traffic in each direction on the west half of 14th street will be maintained at all times during construction.
- One traffic lane on Irving Street will remain open at all times during construction.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restritcted.
- Pedestrian Access to businesses along the side walks will continue to be maintained.
- Pickup & Drop off of riders to the bus stops on 14th Street at Park Rd and Irving St. will be moved temporarily north near Newton St.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular traffic.
Construction Schedule Update (May 17, 2010):
** Work on the Columbia Heights construction project in Final Phase. **
Update
- Construction of Colored Concrete intersection at Irving St continues.
- Pavement Excavation and Road Reconstruction work continues on NB 14th St. (i.e. east side) from Irving Street to Monroe Street.
- Concrete Traffic Barriers remain in place from Irving street to Newton to protect the excavation.
- Concrete Pavement Restoration work on Irving Street (between Hiatt Pl & 14th Street) in progress; remaining piece (at Hiatt Pl) is to be completed by Tuesday May 18, 2010 weather permitting.
- Except for areas marked for decorative banding and public art medallion frames, paver installation work is completed at the Metro Plaza at 3030 14th Street.
- Specialty Lighting installation at Irving St, Park Rd and Kenyon St.
- Solar panel installation at Metro Plaza in progress.
- Water main Tie-ins at Monroe East & West at night.
Changes in Traffic Pattern on 14th Street and Park Road (east side):
- With the Full depth asphalt paving construction on 14th St, traffic from 13th St on Park Rd. is restricted to only one lane in the WB direction;
- The following traffic restrictions at 14th St. & Park Rd. intersection are in place:
- NO right turn onto 14th St.(NB) for traffic from WB Park Rd.(from the Giant)
- NO right turn for traffic from NB 14th onto EB Park RD; Traffic going EB to use Monroe St.
| On-going Construction week of May 10 thur May 22: | |
| Location (1): | NB 14th St. from Irving St to Kenyon St (north half). |
| Work Items: | Roadway reconstruction- aggregate base & base asphalt paving work. |
| Location (2) | NB 14th St. south of Irving St. & south half of Irving St. (east). |
| Work Items: | Pavement Excavation and reconstruction. |
| Location (3): | SE corner of 14th St & Irving St. (east) Intersection |
| Work Items: | Colored Concrete. |
| Location (4): | Irving St. & Metro Plaza |
| Work Items: | Specialty Lighting & Solar Panel installation. |
| Location (5): | Irving Street (from Hiatt Pl to 14th St.) |
| Location (6): | NB 14th St. (i.e. east side) from Irving St. to Monroe St. |
| Work Items: | Pepco & Verizon utility work. |
Night Work Schedule: |
||
| Date | Location | Work Items |
| Tuesday May 18, 2010 | Monroe Street (East & West) | WASA Water main tie-ins. |
Upcoming Work
- Colored Concrete - 14th Street intersections at (1) Irving St. & (2) Kenyon St. and Park Rd.
- Pavement Excavation on 14th Street from Park Rd to Monroe St.
Construction Schedule & Timeline:
14th Street, NW, East Side (North Bound):
| Activity | Location | Estimated Start Date | Estimated End Date (revised) |
| Sidewalk Pavers Installation | Monroe St. to Newton St. | 05/01/10 | Completed* |
| Full Depth Roadway Reconstruction | 14th Street (from Irving St. to Kenyon St.) | In progress | June, 2010 |
| Full Depth Roadway Reconstruction | 14th Street (from Monroe St. to Newton St.) | In progress | 05/14/10 |
| Full Depth Roadway Reconstruction | Monroe Street (East) | In progress | 05/21/10 |
Irving Street (West side of 14th Street):
| Activity | Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Pavement Restoration work | Hiatt Pl. to 15th St. | In progress | 05/18/2010 | One lane closed |
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | complete | complete | complete | N/A | In progress | 6/2010 |
| Park Rd. to Monroe St. | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 06/2010 |
| Monroe St. to Newton St. | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 to 6/2010 |
Maintenance of Traffic (MOT) & Impact:
- East curb lane and inside right lane NB 14th Street will be closed for the road reconstruction and Paving work.
- One lane of traffic in each direction on the west half of 14th street will be maintained at all times during construction.
- One traffic lane on Irving Street will remain open at all times during construction.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restritcted.
- Pedestrian Access to businesses along the side walks will continue to be maintained.
- Pickup & Drop off of riders to the bus stops on 14th Street at Park Rd and Irving St. will be moved temporarily north near Monroe St. and also just south of Irving St. near the CVS store respectively.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular traffic.
Construction Schedule Update (May 10, 2010):
** The Final Phase of the Columbia Heights construction project in progress. **
Update
- First of series of concrete intersections with colored bands was placed at NE corner of 14th Street and Irving Street intersection.
- Pavement Excavation and Road Reconstruction work in progress on NB 14th St. (i.e. east side) from Irving Street to Monroe Street.
- Concrete Traffic Barriers are in placed to protect the excavation.
- Remaining Concrete Pavement Restoration on north half of Irving Street (between Hiatt Pl & 14th Street) continues, and is expected to be completed by Tuesdayday May 11, 2010 weather permitting.
- Except for areas for decorative banding and public art medallion frames, paver installation work is substantially completed at the Metro Plaza at 3030 14th Street.
- Specialty Lighting Installation at Irving St, Park Rd and Kenyon St.
- Water service connections completed; 2 Tie-ins at Monroe East & West only remain.
Changes in Traffic Pattern on 14th Street at Park Road (east side):
- With the Full depth asphalt paving construction on 14th St, traffic from 13th St on Park Rd. is restricted to only one lane in the WB direction;
- The following traffic restrictions at 14th St. & Park Rd. intersection are in place:
- NO right turn onto 14th St.(NB) for traffic from WB Park Rd.(from the Giant)
- NO right turn for traffic from NB 14th onto EB Park RD; Traffic going EB to use Monroe St.
| On-going Construction week of May 10 thur May 22: | |
| Location (1): | NB 14th St. (ie. east side) from Monroe St to Newton St. |
| Work Items: | Pavement Excavation and reconstruction, base asphalt paving work. |
| Location (2) | Kenyon Square & Civic Plaza |
| Work Items: | Specialty Lighting installation. |
| Location (3): | Irving Street (from Hiatt Pl. to 14th St.) |
| Work Items: | Pavement restoration & side walk paver repairs. |
| Location (4): | NB 14th St. (i.e. east side) from Irving St. to Monroe St. |
| Work Items: | Pepco & Verizon utility work. |
| Location (5): | Monroe St. to Newton St. |
| Work Items: | Side walk paver installation. |
Night Work Schedule: |
||
| Date | Location | Work Items |
| Monday or Tuesday May 10 or May 11, 2010 | Monroe Street (East & West) | WASA Water main tie-ins. |
Upcoming Work
- Colored Concrete - 14th Street intersections at (1) Irving St. & (2) Kenyon St. and Park Rd.
- Pavement Excavation on 14th Street from Monroe St to Newton St. (following Full Depth asphalt construction from Park Rd. to Monroe St).
Construction Schedule & Timeline:
14th Street, NW, East Side (North Bound):
| Activity | Location | Estimated Start Date | Estimated End Date (revised) |
| Sidewalk Pavers Installation | Monroe St. to Newton St. | *in progress | *05/15/10 |
| Full Depth Roadway Reconstruction | 14th Street (from Irving St. to Kenyon St.) | In progress | June, 2010 |
| Full Depth Roadway Reconstruction | 14th Street (from Monroe St. to Newton St.) | 05/07/10 | 05/21/10 |
Irving Street (West side of 14th Street):
| Activity | Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Pavement Restoration work | Hiatt Pl. to 15th St. | In progress | 05/11/2010 | One lane closed |
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | complete | complete | complete | N/A | In progress | 6/2010 |
| Park Rd. to Monroe St. | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 06/2010 | 6/2010 |
| Monroe St. to Newton St. | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 to 6/2010 |
Maintenance of Traffic (MOT) & Impact:
- East curb lane and inside right lane NB 14th Street will be closed for the road reconstruction and Paving work.
- One lane of traffic in each direction on the west half of 14th street will be maintained at all times during construction.
- One traffic lane on Irving Street will remain open at all times during construction.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restritcted.
- Pedestrian Access to businesses along the side walks will continue to be maintained.
- Pickup & Drop off of riders to the bus stops on 14th Street at Park Rd and Irving St. will be moved temporarily north near Monroe St. and also just south of Irving St. near the CVS store respectively.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular traffic.
Construction Schedule Update (May 03, 2010):
** The Final Phase of the Columbia Heights construction project in progress. **
Update
- Pavement Excavation and Full depth asphalt paving work has begun and in progress on NB 14th St. (i.e. east side) from Irving Street to Monroe Street.
- Concrete Traffic Barriers have been placed to protect the excavation.
- Remaining Concrete Pavement Restoration on north half of Irving Street (between Hiatt Pl & 14th Streets) continues, and is expected to be completed by Saturday May 08, 2010 weather permitting.
- Except for areas for decorative banding and public art medallion frames, paver installation work is substantially completed at the Metro Plaza at 3030 14th Street.
- Specialty Lighting Installation at Irving St, Park Rd and Kenyon St.
- Water service connections.
Changes in Traffic Pattern on 14th Street at Park Road (east side):
- With the Full depth asphalt paving construction on 14th St, traffic from 13th St on Park Rd. is restricted to only one lane in the WB direction;
- The following traffic restrictions at 14th St. & Park Rd. intersection are in place:
- NO right turn onto 14th St.(NB) for traffic from WB Park Rd.(from the Giant)
- NO right turn for traffic from NB 14th onto EB Park RD; Traffic going EB to use Monroe St.
| On-going Construction May 03, 2010 to May 08, 2010 | |
| Location (1): | Metro Plaza |
| Work Items: | Paver installation & Specialty Lighting installation; |
| Location (2): | Irving Street (from Hiatt Pl. to 14th St.) |
| Work Items: | Pavement restoration & side walk repairs |
| Location (3): | NB 14th St. (i.e. east side) from Irving St. to Monroe St. |
| Work Items: | Pavement Excavation and Full depth asphalt paving work. |
| Location (4): | NB 14th St. (i.e. east side) from Irving St. to Monroe St. |
| Work Items: | Pepco & Verizon utility work. |
| Location (5): | Monroe St. to Newton St. |
| Work Items: | Side walk paver installation & Water Service connections |
Night Work Schedule |
||
| Date | Location | Work Items |
|
Tuesday
May 04, 2010 |
Irving Street & Hiatt Pl & 14th St. | Pipe repair & Fire Hydrant Replacement |
|
Wednesday
May 05, 2010 |
14th St at Fire Dept & Newton St. | WASA Water service connections and Tie-ins |
|
Thursday
May 06, 2010 |
14th St at Fire Dept & Newton St. | WASA Water service connections and Tie-ins |
Upcoming Work
- Colored Concrete - 14th Street intersections at (1) Irving St. & (2) Kenyon St. and Park Rd.
- Pavement Excavation on 14th Street from Monroe St to Newton St. (following Full Depth asphalt construction from Park Rd. to Monroe St).
Construction Schedule & Timeline:
14th Street, NW, East Side (North Bound):
| Activity | Location | Estimated Start Date | Estimated End Date (revised) |
| Sidewalk Pavers Installation | Monroe St. to Newton St. | *in progress | *05/15/10 |
| Full Depth Roadway Reconstruction | 14th Street (from Irving St. to Newton St.) | In progress | June, 2010 |
Irving Street (West side of 14th Street):
| Activity | Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Pavement Restoration work | Hiatt Pl. to 15th St. | In progress | 05/08/2010 | One lane closed |
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | complete | complete | complete | N/A | In progress | 05/2010 to 6/2010 |
| Park Rd. to Monroe St. | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 06/2010 | 05/2010 to 6/2010 |
| Monroe St. to Newton St. | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 to 6/2010 |
Maintenance of Traffic (MOT) & Impact:
-
East curb lane and inside right lane NB 14th Street will be closed for the Full Depth Paving work.
One lane of traffic in each direction on the west half of 14th street will be maintained at all times during construction. - One traffic lane on Irving Street will remain open at all times during construction.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restritcted.
- Pedestrian Access to businesses along the side walks will continue to be maintained.
- Pickup & Drop off of riders to the bus stops on 14th Street at Park Rd and Irving St. will be moved temporarily north near Monroe St. and also just south of Irving St. near the CVS store respectively.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular traffic.
Construction Schedule Update (April 19, 2010):
** The Final Phase of the Columbia Heights construction project in progress. **
Update
- Pavement Excavation and Full depth asphalt paving work has begun and in progress on NB 14th St. (i.e. east side) from Irving Street to Monroe Street.
- Concrete Traffic Barriers have been placed to protect the excavation.
- Remaining Concrete Pavement Restoration on north half of Irving Street (between 15th & 14th Streets) continues, and is expected to be completed by Saturday April 24, 2010 weather permitting.
- Side walk paver installation work continues at the Metro Plaza at 3030 14th Street.
- Specialty Lighting Installation at Irving St, Park Rd and Kenyon St.
Changes in Traffic Pattern on 14th Street at Park Road (east side):
- With the Full depth asphalt paving construction on 14th St, traffic from 13th St on Park Rd. is restricted to only one lane in the WB direction;
- The following traffic restrictions at 14th St. & Park Rd. intersection are in place:
- NO right turn onto 14th St.(NB) for traffic from WB Park Rd.(from the Giant)
- NO right turn for traffic from NB 14th onto EB Park RD; Traffic going EB to use Monroe St.
On-going Construction |
|
| Date: | April 05, 2010 to April 19, 2010 |
| Location (1): | Metro Plaza |
| Work Items: | Paver installation; Specialty Lighting installation; |
| Location (2): | Irving Street (from 15th St. to 14th St.) |
| Work Items: | Pavement restoration & side walk repairs |
| Location (3): | NB 14th St. (i.e. east side) from Irving St. to Kenyon St. |
| Work Items: | Pavement Excavation and Full depth asphalt paving work. |
| Location (4): | NB 14th St. (i.e. east side) from Park Rd. to Monroe St. |
| Work Items: | Pepco Electrical work. |
Upcoming Work
- Colored Concrete 14th Street intersections at (1) Irving St. & (2) Kenyon St. and Park Rd.
- Pavement Excavation on 14th Street from Monroe St to Newton St. (following Full Depth asphalt construction from Park Rd. to Monroe St).
Construction Schedule & Timeline:
14th Street, NW, East Side (North Bound):
| Activity | Location | Estimated Start Date | Estimated End Date (revised) |
| Sidewalk Pavers Installation | Monroe St. to Newton St. | *complete | *03/27/10 |
| Full Depth Roadway Reconstruction | 14th Street (from Irving St. to Newton St.) | In progress | June, 2010 |
Irving Street (West side of 14th Street):
| Activity | Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Pavement Restoration work | 14th St. to 15th St. | In progress | 04/23/2010 | One lane closed |
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | complete | complete | complete | N/A | In progress | 05/2010 |
| Park Rd. to Monroe St. | 04/2010 | 04/2010 | 04/2010 | 04/2010 | 04/2010 | 05/2010 |
| Monroe St. to Newton St. | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 |
Maintenance of Traffic (MOT) & Impact:
-
East curb lane and inside right lane NB 14th Street will be closed for the Full Depth Paving work.
One lane of traffic in each direction on the west half of 14th street will be maintained at all times during construction. - One traffic lane on Irving Street will remain open at all times during construction.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restritcted.
- Pedestrian Access to businesses along the side walks will continue to be maintained.
- Pickup & Drop off of riders to the bus stops at Park Road & Irving St. will be moved temporarily to north near Monroe St. and also just south of Irving St. near the CVS store respectively.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular traffic.
Construction Schedule Update (April 05, 2010):
** The Columbia Heights construction project enters its final phase. **
Update
- Pavement Excavation and Full depth asphalt paving work has begun and in progress on NB 14th St. (i.e. east side) from Park Rd. to Monroe St. through April 18, 2010 weather permitting.
- Concrete Traffic Barriers have been placed starting on April 02, 2010 to protect the excavation.
- Except service connections (between Monroe & Newton Sts.), major work on the WASA Water main replacement on 14th Street is completed.
- Concrete Pavement Restoration on Irving Street (between 15th & 14th Streets) continues.
- Side walk paver installation work continues at the Metro Plaza at 3030 14th Street.
Changes in Traffic Pattern on 14th Street at Park Road:
- With the Full depth asphalt paving construction on 14th St. from Park Rd to Monroe St., traffic from 13th St on Park Rd. is restricted to only one lane in the WB direction;
- The following traffic restrictions at 14th St. & Park Rd. intersection are in place:
- NO right turn onto 14th St.(NB) for traffic from WB Park Rd.(from the Giant)
- NO right turn for traffic from NB 14th onto EB Park RD; Traffic going EB to use Monroe St.
On-going Construction |
|
| Date: | April 05, 2010 to April 19, 2010 |
| Location (1): | Metro Plaza & Irving St. |
| Work Items: | Side walk & paver installation; Specialty Lighting installation |
| Location (2): | Irving Street (from 15th St. to 14th St.) |
| Work Items: | Pavement restoration & side walk repairs |
| Location (3): | NB 14th St. (i.e. east side) from Park Rd. to Monroe St. |
| Work Items: | Pavement Excavation and Full depth asphalt paving work. |
Upcoming Work
- Colored Concrete 14th Street intersections at (1) Irving St. & (2) Kenyon St. and Park Rd.
- Pavement Excavation on 14th Street from Monroe St to Newton St. (following Full Depth asphalt construction from Park Rd. to Monroe St.) – from April 19, 2010.
Construction Schedule & Timeline:
14th Street, NW, East Side (North Bound):
| Activity | Location | Estimated Start Date | Estimated End Date (revised) |
| Sidewalk Pavers Installation | Monroe St. to Newton St. | *Substantially complete | *03/27/10 |
| Full Depth Roadway Reconstruction | 14th Street (from Irving St. to Newton St.) | In progress | June, 2010 |
Irving Street (West side of 14th Street):
| Activity | Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Pavement Restoration work | 14th St. to 15th St. | In progress | 04/04/2010 | TBD |
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | complete | In progress | In progress | N/A | In progress | 05/2010 |
| Irving St. to Park Rd. | N/A | N/A | N/A | N/A | N/A | 05/2010 |
| Park Rd. to Monroe St. | 04/2010 | 04/2010 | 04/2010 | 04/2010 | 04/2010 | 05/2010 |
| Monroe St. to Newton St. | 04/2010 | 04/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 |
Maintenance of Traffic (MOT) & Impact:
-
East curb lane and inside right lane NB 14th Street will be closed.
One lane of traffic in each direction on the west half of 14th street will be maintained at all times during construction. - One traffic lane on Irving Street will remain open at all times during construction.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restritcted.
- Pedestrian Access to businesses along the side walks will continue to be maintained.
- Pickup & Drop off of riders to the bus stops at Park Road & 14th Street will be moved temporarily to north near Monroe St.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular traffic.
Construction Schedule Update (March 19, 2010):
Update
- Pavement Excavation and Full depth asphalt paving work begins starting on Monday, March 29, 2004 on NB 14th St. (i.e. east side) from Park Rd. to Monroe St.
- Concrete Traffic Barriers will be placed starting on Friday March 26, 2010 to protect the excavation.
- Work continues on the west half (final phase of streetscape work) on 14th Street.
- Except for testing and service connections (at north of Monroe St.), major work on the WASA Water main replacement on 14th Street is completed. Testing, service connections and tie-in to existing at Newton St. is scheduled for the week of March 29, 2010.
- Pavement Restoration on Irving Street (between 15th & 14th Streets)
Anticipated New Traffic Pattern on Park Road
- Starting on or about April 05, 2010, when Full depth construction from Park Rd to Monroe St. is completed, WB traffic from 13th St will no longer be able to turn left onto 14th St. or continue on Park RD across 14th St; WB traffic can only turn right to go NB on 14th St. at Park Rd.
On-going Construction |
|
| Date: | March 22,2010 to April 03, 2010 |
| Location (1): | Metro Plaza & Irving St. |
| Work Items: | Sidewalk & paver installation; Specialty Lighting installation; Streetlight pole foundations; Pavement Restoration on Irving St. (from 15th St. to 14th St.) |
| Location (2): | West side of 14th St. from Columbia Road to Irving Street; |
| Work Items: | Sidewalk & paver installation; Streetlight pole foundations; |
| Location (3): | 14th St from Monroe St to Newston St. (east side) |
| Work Items: | WASA watermain line; Sidewalk & paver installation; |
Upcoming Work
- Concrete intersections
- Pavement Excavation on 14th Street from Monroe St to Newton St. (starting on April 05, 2010)
Construction Schedule & Timeline
14th Street, NW, East Side (North Bound), from Park Rd. to Newton St:| Activity | Location | Estimated Start Date | Estimated End Date (revised) |
| Sidewalk Pavers Installation | Monroe St. to Newton St. | In progress | 03/27/10 |
| Full Depth Roadway Reconstruction | Irving St. to Newton St. | May 2010 | June 2010 |
Irving Street (West side of 14th Street): Electrical Installation
| Activity | Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Pavement Restoration work | 14th St. to 15th St. | In progress | 04/04/2010 | TBD |
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | N/A | In progress | In progress | N/A | In progress | 05/2010 |
| Irving St. to Park Rd. | N/A | N/A | N/A | N/A | N/A | 05/2010 |
| Park Rd. to Monroe St. | 04/2010 | 04/2010 | 03/2010 | 04/2010 | 04/2010 | 05/2010 |
| Monroe St. to Newton St. | 04/2010 | 04/2010 | 05/2010 | 05/2010 | 05/2010 | 05/2010 |
Maintenance of Traffic (MOT)
-
East curb lane and inside right lane NB 14th Street will be closed.
One lane of traffic in each direction will be maintained at all times during construction. - At least one traffic lane in each direction on 14th Street will remain open at all times during construction.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restritcted
- Pedestrian Access to businesses along the west sidewalks will continue to be maintained.
- Pickup & Drop off of riders to the bus stop at Park Road & 14th Street will be moved temporarily to north near Monroe St.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
Snow emergency declared in the District as a result of the recent snow storm affected the progress of work.
Construction Schedule Update (February 28, 2010):
**Work on the west half (final phase of streetscape work) on 14th Street has begun.
*Except for service connections to DCUSA, the WASA Water main replacement on 14th Street (the section from Irving Street to Park Rd) is completed; Work on the final section is in progress and at currently at Monroe Street intersection and continues along the west curb lane (SB) on 14th Street, NW.| Current Location | End Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Monroe Street | Newton Street | In progress |
March 15, 2010 due to weather delay |
Curb lane & right inside lane on SB 14th St. |
- One lane of traffic in each direction on 14th St. will be maintained at ALL times during construction.
- All businesses along the sidewalks are not expected to be impacted and are expected to remain open during construction and access will not be restricted.
- Traffic Safety Officers at Intersections during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
General WORK SEQUENCE
East Side: Monroe St to Newton StWest Side: Irving St to Park Rd; Park Rd to Monroe St; Monroe St to Newton:
Details of Work are as follows:
14th Street, NW, East Side (North Bound), from Park Rd. to Newton St:| Activity | Location | Estimated Start Date | Estimated End Date |
| Granite Curb Installation | Monroe St. to Newton St. | Completed | Completed |
| Sidewalk Pavers Installation | Park Rd. to Newton St. | Completed | Completed |
| Street light ducts & pole foundations | Park to Newton St. | Completed | Completed |
| Storm drainage | Monroe St. to Newton St. | Completed | Completed |
| Utilities | Monroe St. to Newton St. | Installation completed | Installation completed |
| Landscape/Trees | Park Rd. to Monroe St. | Completed | Completed |
| Landscape/Trees | Monroe St to Newton St | In progress | 03/23/2010 |
| Full Depth Roadway Reconstruction | Irving St. to Newton St. | May 2010 | June 2010 |
- Anticipated Lane Closure (MOT): East curb lane and inside right lane NB 14th St.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restricted.
- Pedestrian Access to businesses along the east side walks (including Tivoli Theatre) will continue to be maintained.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
Irving Street (West side of 14th Street): Electrical Installation:
| Activity | Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Street light laterals & pole foundations | 14th St. to 15th St. | Completed | Completed | Daily off-peak closures |
| Upgrade of Storm Structures & sidewalk work | 14th St. to Hiatt Pl. | In progress | 03/30/2010 | As needed |
| Pavement Restoration work | 14th St. to 15th St. | 04/2010 | 05/2010 | TBD |
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | N/A | In progress | In progress | N/A | In progress | 4/2010 |
| Irving St. to Park Rd. | N/A | N/A | N/A | N/A | N/A | 4/2010 |
| Park Rd. to Monroe St. | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 4/2010 |
| Monroe St. to Newton St. | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 4/2010 |
- Anticipated Lane Closure (MOT): West curb lane and inside right lane SB 14th St.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restricted.
- Pedestrian Access to businesses along the west side walks (including entrance to the Kelsey Apartments) will continue to be maintained.
- Pickup & Drop off of riders to the bus stop at Park & 14th will be moved temporarily north near Monroe St.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
Snow emergency declared in the District as a result of the recent snow storm affected the progress of work.
Construction Schedule Update (January 18, 2010):
*WASA Water main replacement work on 14th Street has begun:
This work is anticipated to take 45 days to complete and will be along the west curb lane (SB) on 14th Street, NW| Start Location | End Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Irving Street | Newton | In progress | March 01, 2010 |
Curb lane & right inside lane on SB 14th St. |
- One lane of traffic in each direction on 14th St. will be maintained at ALL times during construction.
- All businesses along the sidewalks are not expected to be impacted and are expected to remain open during construction and access will not be restricted.
- Traffic Safety Officers at Intersections during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
14th Street, NW, East Side (North Bound) from Park Rd to Newton St:
| Activity | Location | Estimated Start Date | Estimated End Date |
| Granite Curb Installation | Monroe St. to Newton St. | In Progress | 01/23/10 |
| Sidewalk Pavers Installation | Park Rd. to Newton St. | In Progress | 01/30/10 |
| Street light ducts & pole foundations | Park to Newton St. | In Progress | 01/21/10 |
| Storm drainage | Monroe St. to Newton St. | In Progress | 02/2010 |
| Utilities | Monroe St. to Newton St. | 12/14/09 | 02/2010 |
| Landscape/Trees | Park Rd. to Newton St. | 02/2010 | 02/2010 |
| Full Depth Roadway Reconstruction | Irving St. to Newton St. | May 2010 | June 2010 |
- Anticipated Lane Closure (MOT): East curb lane and inside right lane NB 14th St.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restricted.
- Pedestrian Access to businesses along the east side walks (including Tivoli Theatre) will continue to be maintained.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
Irving Street (West side of 14th Street): Electrical Installation:
| Activity | Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Street light laterals & pole foundations | 14th St. to 15th St. | In Progress | 01/25/10 | Daily off-peak closures |
| Upgrade of Storm Structures & sidewalk work | 14th St. to Hiatt Pl. | 04/2010 | 05/2010 | TBD |
| Pavement Restoration work | 14th St. to 15th St. | 04/2010 | 05/2010 | TBD |
14th Street, NW, West Side (South Bound): this work will follow behind the WASA water main work installation work.
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Utilities | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | N/A | N/A | N/A | N/A | N/A | N/A | 4/2010 |
| Irving St. to Park Rd. | N/A | N/A | N/A | N/A | N/A | N/A | 4/2010 |
| Park Rd. to Monroe St. | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 4/2010 |
| Monroe St. to Newton St. | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 4/2010 |
- Anticipated Lane Closure (MOT): West curb lane and inside right lane SB 14th St.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restricted.
- Pedestrian Access to businesses along the west side walks (including entrance to the Kelsey Apartments) will continue to be maintained.
- Pickup & Drop off of riders to the bus stop at Park & 14th will be moved temporarily north near Monroe St.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
Construction Schedule Update (December 22, 2009):
14th Street, NW, East Side (North Bound), from Park Rd. to Newton St:
| Activity | Location | Estimated Start Date | Estimated End Date |
| Granite Curb Installation | Monroe St. to Newton St. | In progress | 12/30/09 |
| Sidewalk Pavers Installation | Park Rd to Newton St. | In progress | 12/30/09 |
| Street light ducts & pole foundations | Park to Newton St. | In progress | 12/30/09 |
| Storm drainage | Monroe St. to Newton St. | 12/14/09 | 02/2010 |
| Utilities | Monroe St. to Newton St. | 12/14/09 | 02/2010 |
| Landscape/Trees | Park Rd to Newton St. | 02/2010 | 02/2010 |
| Full Depth Roadway Reconstruction | Irving St. to Newton St. | May, 2010 | June, 2010 |
Anticipated Lane Closure (MOT): East curb lane and inside right lane NB 14th St.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restricted.
- Pedestrian Access to businesses along the east side walks (including Tivoli Theatre) will continue to be maintained.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
Irving Street (West side of 14th Street): Electrical Installation:
| Activity | Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Street light Ducts & pole foundations | 14th St. to 15th St. | 12/15/09 | 01/08/10 | Daily off-peak closures |
| Upgrade of Storm Structures & sidewalk work | 14th St. to Hiatt Pl. | 04/2010 | 05/2010 | TBD |
| Pavement Restoration work | 14th St. to 15th St. | 04/2010 | 05/2010 | TBD |
14th Street, NW, West Side (South Bound):
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Utilities | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | N/A | N/A | N/A | N/A | N/A | N/A | 4/2010 |
| Irving St. to Park Rd. | N/A | N/A | N/A | N/A | N/A | N/A | 4/2010 |
| Park Rd. to Monroe St. | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 4/2010 |
| Monroe St. to Newton St. | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 4/2010 |
Anticipated Lane Closure (MOT): West curb lane and inside right lane SB 14th St.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restricted.
- Pedestrian Access to businesses along the west side walks (including entrance to the Kelsey Apartments) will continue to be maintained.
- Pickup & Drop off of riders to the bus stop at Park & 14th will be moved temporarily north near Monroe St.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
WASA Water main replacement schedule:
Work is anticipated to be along the west half of the Roadway on 14th Street, NW;| Start Location | End Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Irving Street | Newton | January 02, 2010 | March 01, 2010 | Curb lane & right inside lane SB 14th St. |
- All businesses along the sidewalks are not expected to be impacted and are expected to remain open during construction and access will not be restricted.
- Traffic Safety Officers at Intersections during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
Temporarily Re-route of H8 Bus
Due to safety concerns, there will be no parking at any time in the construction zone until further notice.
14th Street construction Progress Update
December 8, 2009 Update
Construction Schedule Update:
- Construction will continue on the east side of 14th Street, NW, between Park Rd and Newton Street, NW thru the end of December and into early January 2010.
- Construction items include but is not limited to, granite curbs, light pole foundation, modification of storm drains and structures, sidewalk widening and paver installation, electric ducts, traffic signal modification at intersections, installation of Park Benches, new tree pits/Landscaping.
- The new Watermain line construction along 14th Street from Irving Street to Newton Street is scheduled to begin on or by January 02, 2010.
- All existing pedestrian and traffic safety systems in place will continue to be implemented with modifications as conditions dictate.







Notice of Proposed CRT Meeting
November 9, 2009 Update
The District Department of Transportation invites you to attend a Community Relations Team meeting for the Columbia Heights Streetscape Project.
The purpose of the meeting is to provide updates on construction work on 14th Street NW, the civic plaza, and Irving Street NW.
Date & Time: Thursday, November 12, 2009
6:30 – 7:30pm
Location: Columbia Heights Streetscape Project Office
3247 Mt. Pleasant Street, NW
Washington, DC 20010
For more information: Telephone: 202-234-7551
Resident Engineer,
Mr. Vincent Kumordzie, P.E.
DDOT Project Engineer,
Mr. Deinma Jamabo
Visit our project office:
3247 Mt. Pleasant Street, NW
Monday—Friday, 7am - 4pm
MOT UPDATE
November 9, 2009 Update
Proposed MOT on NB 14th Street – November 02 thru November 20, 2009
Location: from Park Road to Monroe Street:
-
The NB lane and the parking/curb lane will be closed at all times during construction. One lane of traffic in both direction on 14th Street will be maintained at all times during this time.
Construction Activities to be performed:
-
Work to be performed include but is not limited to; removal of existing curb & side walk; installation of new granite curbs, side walk reconstruction with pavers, storm drain inlet installation, Duct for Specialty Single stem Lighting , Street Light foundation and pole installation.
Note:
-
All businesses along the sidewalks are expected to remain open during construction and access will not be restricted.
-
Pedestrian Access to businesses along the east side walks (including Tivoli Theatre) will be maintained.
-
Traffic Safety Officers, Flagmen and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
-
Intermittent stoppages utilizing flagmen and or TOC’s may be used for movement of equipment in and out of work zones during construction;
-
Traffic Safety Officers, Flagmen and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
-
Park Road (East) within the 1300 block from 14th St., NW to the Giant Store will periodically be reduced to one lane (west bound only) from 7:00am to 7:00pm when work on the north curbline & side walk is conducted. An arrow board & VMS board will be used to notify motorists of the closure.
-
Vehicular access to and from the Giant and the parking facility east of the Giant will be from Homestead Pl and 13th St. NW. when Park road is reduced to WB traffic only.
-
When possible and safe, the road way will be opened to traffic at the close of operations each day during this period.
Construction work moves to the 3300 block of 14th St.
Beginning October 19, 2009, construction activities on 14th Street, NW will be moving to the east side of the 3300 block, from Park Road to Monroe Street, NW. One lane of northbound and one lane of southbound traffic will be maintained on 14th Street at all times. However, the east half of 14th Street, including the traffic lane and the parking lane, will be closed at all times during construction.
Construction Details
Work to be performed includes but is not limited to removal of the existing curb and sidewalk, the installation of new granite curbs, storm drain inlets, street light foundations and poles, and sidewalk reconstruction with pavers at the civic plaza.
- Sidewalk and pedestrian access to businesses will be maintained at all times, including the Park Road sidewalk east of 14th Street.
- Traffic safety officers, flagmen and VMS message boards will be utilized to assist in directing the flow of pedestrian and vehicular traffic.
- No parking will be allowed within the block during construction.
Columbia Heights Civic Plaza work
completed:
Fenty Administration to Unveil New Columbia
Heights Plaza



DDOT Nearing Completion of Initial Phase of Columbia Heights Streetscape Project
Work Now Moves Forward on 14th Street, NW
The District Department of Transportation (DDOT) is close to completing the initial phase of the Columbia Heights streetscape project. The work on Park Road, between Mount Pleasant and 16th Street is completed.
Surface asphalt paving from 16th Street to 14th Street and new paver side walk work as well as the construction that is ongoing in the Civic Plaza, located at the intersection of Kenyon Street, 14th Street and Park Road, NW, are scheduled to be completed on or about by the first week of August, weather permitting.
DDOT will then move forward with improvements on 14th Street, NW, including new storm drain inlets, sidewalks, granite curbs and streetlights.
To facilitate this work safely, the right travel lane and curb parking lane on northbound 14th Street, from Columbia Road to Park Road, will be closed beginning on or about Monday, July 27, 2009. One lane of traffic will be maintained in both directions at all times during the construction.
Loss of some parking spaces in the 3000 block of 14th Street on both sides of the roadway because of the new temporary lane configuration is anticipated. Motorists are encouraged to use the DCUSA parking facility - there are entrances to the garage on Park Road and Hiatt Place – or take mass transit. Columbia Heights is served by Metrorail’s Green and Yellow lines, as well as Metrobus and the DC Circulator.
Please note, there will be some bus stop and route changes for the safety of passengers:
-
The pick-up of H8 passengers will be relocated from 14th Street to the Irving Street bus stop near the Metro Station entrance.
-
Instead of turning northbound on 14th Street, the H8 bus will continue east on Irving Street.
-
All passengers using the bus stop on 14th Street, north of Irving Street, will use a temporary stop just south of Irving near the CVS and Bank of America.
The businesses in Columbia Heights will remain open during the construction and every effort will be made to maintain access to the sidewalks. There may be some temporary sidewalk closures and detours will be posted for pedestrians. Variable message boards will also be used to alert drivers to the traffic pattern changes.
More extensive road reconstruction work on 14th Street, from Newton Street to Columbia Road, is scheduled to begin in November. DDOT will also be reconstructing Irving Street, between 14th and 16th Streets, and the entire project is expected to be completed in late spring, 2010.
Overall, the improvements to the Columbia Heights area include total roadway reconstruction, waterline and drainage upgrades, new sidewalks, landscaping, street lighting, intersection and signal improvements, enhancements to traffic operations, pedestrian amenities and safety improvements.
For more information about the project, residents can visit the project website at www.columbiaheights-streetscape.com or the field office at 3247 Mt. Pleasant Street, NW, Monday through Friday, between 8 a.m. and 4 p.m.








What is the Columbia Heights Streetscape?
The District of Columbia Department of Transportation (DDOT) is making improvements along Park Road, 14th Street, and Irving Street to include:
- Waterline and drainage upgrades
- Sidewalk, curb and gutter upgrades
- Roadway reconstruction
- Construction of a civic plaza and fountain
- Landscaping and street lighting
- Intersection, signal and safety improvements
- Pedestrian amenities
Construction, Traffic and Parking Guidelines
- Work within only two blocks will be allowed at a time
- At least one (1) lane of traffic in each direction will be kept open at all times
- Temporary weekend intersection closures or detours of certain traffic movements will be allowed to facilitate the construction of special intersection concrete paving
- “No Parking” signs will only be in effect two blocks at a time. As much as possible, parking restrictions will only be in place from 7:00am to 7:00pm, Monday - Saturday
- Community will receive a minimum of two week advance notification of construction work and parking restrictions
- Contractor and project team will work with affected businesses to provide proper accommodations for delivery, trash collection schedules, etc.
The project area for these phases will include:
Phase I:
- Park Road, NW from Mt Pleasant Street to 14th Street
- Civic Plaza with Fountain
Phase II:
- 14th Street, NW from Newton Street to Columbia Road
- Irving Street, NW from 16th Street to 14th Street
Project Area Map
Click image below for larger version. (Or download the full-sized image, 4.4MB)
Previous Plans
- Columbia Heights/Mount Pleasant Transportation Study
- Mount Pleasant Transportation Study
- Columbia Heights Public Realm Framework Plan
September 08, 2009 Update
Closure Of Park Road Nw: Continuation Of Work At The Plaza
Beginning Tuesday September 08, through Saturday September 12, 2009, approximately 100 ft section of Park Road (east) within the 1300 block from 14th St., NW to the Giant Store will be closed from 7:00 AM to 7:00 PM for Light Pole installation work at the Civic Plaza. Due to safety concerns as well as the size of crane to be used, vehicular traffic through this portion of Park Road will be prohibited during installation operations.
Sidewalks remain open during this Light Pole installation operation and access to all buildings (including Giant Food Store and Park Triangle building) will be maintained.
Vehicular access to and from the Giant Store and the parking facility east of the Giant will be from Homestead Pl and 13th St. NW. Traffic Safety Officers, Flagmen and Portable Changeable Message Signs will be utilized to assist in directing the flow of both pedestrian and vehicular.
The road way will be opened to traffic at the close of operations each day during this period.
March 30, 2009 Update
The March 26 slide presentation is now posted on our Public Meetings page.
March 13, 2009 Update
The H8 bus route has been temporarily re-routed from the 1600 block of Park Road NW. Please board at the Mt. Pleasant and 17th Street terminal bus stop until construction is clear on Park Road.
March 11, 2009 Update
New sidewalk on the south side of 1600 block of Park Road facing east.
February 16, 2009 Update
The January 2009 project newsletter is available in English and Spanish.
February 3, 2009 Update
The January 29 slide presentation is now posted on our Public Meetings page.
January 29, 2009 Update
Public drop-in hours at the project field office are now Thursdays from 1-5 p.m., or by appointment. Click here for more information on how to contact us.
January 7, 2009 Update
Due to safety concerns, there will be no parking at any time in the construction zone on the 1500 and 1600 blocks of Park Road, NW until further notice.
December 26, 2008 Update
The December 2008 project newsletter is now available in English and Spanish.
December 12, 2008 Update
Residents of the 1600 Block of Park Road NW are now eligible for Zone 1 Residential Parking Permits. Click here for more information.
December 8, 2008 Update
DC Department of Transportation Begins Road Construction on Park Road NW. Click here for more information.
Viewing construction from the intersection of Park Road, NW and Mt. Pleasant Street, NW
Construction on the 1600 block of Park Road, NW
Construction signage on Park Road at Hiatt Place, NW
November 1, 2008 Update
View of 14th Street from Park Road, NW
Plaza Area at 14th St., NW
Park Road at Hiatt Pl, NW