Construction Schedule Update (July 26, 2010):

** Work on the Columbia Heights construction project in Final Phase. **

Update

  • Final surface asphalt paving completed on 14th St. from Columbia Rd. to Newton St.
  • Pavement marking on All areas within Project limits.
  • Installation of Art Medallion at Metro completed.
  • Final cable installation for Streetlights and Traffic Signal Light Installation in progress.
  • Final phase of Side walk reconstruction and paver installation on west side of 14th St from Park rd to Newton Street in progress.
  • Final phase of Landscaping from Park to Newton.
  • General Clean up and Punchlist.

Changes in Traffic Pattern on 14th Street and Park Road:

    1. EB Park Rd is now open to traffic from 14th St; Right turn from NB 14th St is now open.
    2. WB Park Rd traffic from Holmead Pl can only turn right onto NB 14th St. at the 14th St. intersection.
    3. No thru traffic for WB Park Rd. traffic across 14th St. to Park Rd (west).
    4. Motorist from the east of 14th St. wishing to go west on Park Rd may now use Kenyon St.
Upcoming Work:
  • Removal of existing streetlight poles and traffic signal poles.
On-going Construction     Week of July 26 thru July 30:
Location (1): 14th Street- from Park Rd to Newton (West side)
Work Items: Sidewalk Paver installation
Location (2): 14th St- NW corner of Newton St. (West side)
Work Items: Excavation of existing sidewalk and place PCC base for Sidewalk Paver Installation.
Location (3): 14th St- from Havard St to Newton St.
Work Items: Pavement marking and general site cleanup.
Location (4): 14th St- from Park Rd to Newton St & Intersections from Irving St.
Work Items: Electrical cable and hardware installation for Traffic Signal lights and Streetlights.
Location (5): 14th St- from Columbia Rd to Newton
Work Items: Signs.
Location (6): 14th St- from Columbia Rd to Newton
Work Items: Punch list work.

Upcoming Work

  • Punchlist work, general clean up and Project close out.

Construction Schedule & Timeline:

14th Street, NW, West Side (South Bound):

Activity/Location Granite Curb Installation Sidewalk Pavers Installation Street light ducts & pole foundations Storm drainage Landscape/ Trees Full depth Roadway Reconstruction
Columbia Rd to Irving St. Complete Complete Complete N/A In progress Complete
Park Rd to Monroe St. Complete 06/2010 06/2010 06/2010 07/2010 07/2010
Monroe St to Newton St. 07/2010 07/2010 07/2010 07/2010 07/2010 07/2010
Columbia Rd to Newton St. Punchlist Punchlist Punchlist Punchlist Punchlist Punchlist

Maintenance of Traffic (MOT) & Impact:

  • All lanes opened to traffic from Columbia Road to Newton St.
  • All businesses along the sidewalks are expected to remain open during paver installation work and access will not be restritcted.
  • Pedestrian Access to businesses along the side walks will continue to be maintained during paver installation work.
  • Crosswalks are now open all over the project, except where affected by unit paver installation work.
  • Traffic Safety Officers at Intersections during rush-hour, Flagmen (where needed for cleanup and to remove equipment and material for unit paving installation).
************ All Work/Schedule Dependent On Weather. ************

Irving St & Metro Plaza

Irving St West

14th St & Park Paving

Striping Irving St South