Construction Schedule Update (January 18, 2010):
*WASA Water main replacement work on 14th Street has begun:
This work is anticipated to take 45 days to complete and will be along the west curb lane (SB) on 14th Street, NW| Start Location | End Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Irving Street | Newton | In progress | March 01, 2010 |
Curb lane & right inside lane on SB 14th St. |
- One lane of traffic in each direction on 14th St. will be maintained at ALL times during construction.
- All businesses along the sidewalks are not expected to be impacted and are expected to remain open during construction and access will not be restricted.
- Traffic Safety Officers at Intersections during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
14th Street, NW, East Side (North Bound) from Park Rd to Newton St:
| Activity | Location | Estimated Start Date | Estimated End Date |
| Granite Curb Installation | Monroe St. to Newton St. | In Progress | 01/23/10 |
| Sidewalk Pavers Installation | Park Rd. to Newton St. | In Progress | 01/30/10 |
| Street light ducts & pole foundations | Park to Newton St. | In Progress | 01/21/10 |
| Storm drainage | Monroe St. to Newton St. | In Progress | 02/2010 |
| Utilities | Monroe St. to Newton St. | 12/14/09 | 02/2010 |
| Landscape/Trees | Park Rd. to Newton St. | 02/2010 | 02/2010 |
| Full Depth Roadway Reconstruction | Irving St. to Newton St. | May 2010 | June 2010 |
- Anticipated Lane Closure (MOT): East curb lane and inside right lane NB 14th St.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restricted.
- Pedestrian Access to businesses along the east side walks (including Tivoli Theatre) will continue to be maintained.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
Irving Street (West side of 14th Street): Electrical Installation:
| Activity | Location | Estimated Start Date | Estimated End Date | Lane Closure |
| Street light laterals & pole foundations | 14th St. to 15th St. | In Progress | 01/25/10 | Daily off-peak closures |
| Upgrade of Storm Structures & sidewalk work | 14th St. to Hiatt Pl. | 04/2010 | 05/2010 | TBD |
| Pavement Restoration work | 14th St. to 15th St. | 04/2010 | 05/2010 | TBD |
14th Street, NW, West Side (South Bound): this work will follow behind the WASA water main work installation work.
| Activity/Location | Granite Curb Installation | Sidewalk Pavers Installation | Street light ducts & pole foundations | Storm drainage | Utilities | Landscape/ Trees | Full depth Roadway Reconstruction |
| Columbia Rd to Irving St. | N/A | N/A | N/A | N/A | N/A | N/A | 4/2010 |
| Irving St. to Park Rd. | N/A | N/A | N/A | N/A | N/A | N/A | 4/2010 |
| Park Rd. to Monroe St. | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 4/2010 |
| Monroe St. to Newton St. | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 03/2010 | 4/2010 |
- Anticipated Lane Closure (MOT): West curb lane and inside right lane SB 14th St.
- All businesses along the sidewalks are expected to remain open during construction and access will not be restricted.
- Pedestrian Access to businesses along the west side walks (including entrance to the Kelsey Apartments) will continue to be maintained.
- Pickup & Drop off of riders to the bus stop at Park & 14th will be moved temporarily north near Monroe St.
- Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.