Construction Schedule Update (January 18, 2010):

*WASA Water main replacement work on 14th Street has begun:

This work is anticipated to take 45 days to complete and will be along the west curb lane (SB) on 14th Street, NW
Start Location End Location Estimated Start Date Estimated End Date Lane Closure
Irving Street Newton In progress March 01, 2010 Curb lane & right inside lane on
SB 14th St.
  • One lane of traffic in each direction on 14th St. will be maintained at ALL times during construction.
  • All businesses along the sidewalks are not expected to be impacted and are expected to remain open during construction and access will not be restricted.
  • Traffic Safety Officers at Intersections during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.

14th Street, NW, East Side (North Bound) from Park Rd to Newton St:

Activity Location Estimated Start Date Estimated End Date
Granite Curb Installation Monroe St. to Newton St. In Progress 01/23/10
Sidewalk Pavers Installation Park Rd. to Newton St. In Progress 01/30/10
Street light ducts & pole foundations Park to Newton St. In Progress 01/21/10
Storm drainage Monroe St. to Newton St. In Progress 02/2010
Utilities Monroe St. to Newton St. 12/14/09 02/2010
Landscape/Trees Park Rd. to Newton St. 02/2010 02/2010
Full Depth Roadway Reconstruction Irving St. to Newton St. May 2010 June 2010
  • Anticipated Lane Closure (MOT): East curb lane and inside right lane NB 14th St.
  • All businesses along the sidewalks are expected to remain open during construction and access will not be restricted.
  • Pedestrian Access to businesses along the east side walks (including Tivoli Theatre) will continue to be maintained.
  • Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.

Irving Street (West side of 14th Street): Electrical Installation:

Activity Location Estimated Start Date Estimated End Date Lane Closure
Street light laterals & pole foundations 14th St. to 15th St. In Progress 01/25/10 Daily off-peak closures
Upgrade of Storm Structures & sidewalk work 14th St. to Hiatt Pl. 04/2010 05/2010 TBD
Pavement Restoration work 14th St. to 15th St. 04/2010 05/2010 TBD

14th Street, NW, West Side (South Bound): this work will follow behind the WASA water main work installation work.

Activity/Location Granite Curb Installation Sidewalk Pavers Installation Street light ducts & pole foundations Storm drainage Utilities Landscape/ Trees Full depth Roadway Reconstruction
Columbia Rd to Irving St. N/A N/A N/A N/A N/A N/A 4/2010
Irving St. to Park Rd. N/A N/A N/A N/A N/A N/A 4/2010
Park Rd. to Monroe St. 03/2010 03/2010 03/2010 03/2010 03/2010 03/2010 4/2010
Monroe St. to Newton St. 03/2010 03/2010 03/2010 03/2010 03/2010 03/2010 4/2010
  • Anticipated Lane Closure (MOT): West curb lane and inside right lane SB 14th St.
  • All businesses along the sidewalks are expected to remain open during construction and access will not be restricted.
  • Pedestrian Access to businesses along the west side walks (including entrance to the Kelsey Apartments) will continue to be maintained.
  • Pickup & Drop off of riders to the bus stop at Park & 14th will be moved temporarily north near Monroe St.
  • Traffic Safety Officers at Intersection during rush-hour, Flagmen (at crosswalks within the construction zone) and VMS message boards will be utilized to assist in directing the flow of both pedestrian and vehicular.
************ NOTE: All Work/Schedule Dependent On Weather. ************